Record Data Sheet

Amount
$80B
Entity
Microsoft
Vertical
Tech · AI infrastructure
Record Type
Annual spending plan
Previous Record
$55.7B (fiscal 2024 capex, incl. finance leases)
Period
Fiscal 2025 (July 2024 to June 2025)
Confirmed
January 3, 2025

On January 3, 2025, Microsoft vice chair and president Brad Smith published a post on the company’s blog with a single number at its center. Microsoft, he wrote, was on track to invest about $80 billion in fiscal 2025 to build out AI-enabled datacenters, and more than half of that would be spent in the United States. Microsoft’s fiscal year runs from July to June, so the figure covered July 2024 through June 2025, and by the time the post went up, half of that period had already passed.

The figure was presented as a plan, not as a result. The results came later, one quarter at a time, in the remarks the company’s chief financial officer, Amy Hood, gives on every earnings call.

What the quarterly reports show

Microsoft reports a measure it calls capital expenditures including finance leases. It counts cash spent on property and equipment plus the full value of datacenter leases at the moment they start. Across fiscal 2025, the four quarterly figures were $20.0 billion, $22.6 billion, $21.4 billion and $24.2 billion. Added together, that is $88.2 billion.

The year before, the same measure came to $55.7 billion ($11.2 billion, $11.5 billion, $14.0 billion and $19.0 billion). Fiscal 2025 was therefore about 58% higher than fiscal 2024.

Chart: Microsoft cumulative capex by quarter in fiscal 2025, reaching $88.2 billion against the $80 billion AI datacenter plan.

Why $88.2 billion and $80 billion are not the same thing

It would be easy to say Microsoft spent $8 billion more than it promised. The documents do not support that reading. The $80 billion in the January post referred specifically to AI-enabled datacenters. The $88.2 billion is total capital expenditure, including finance leases, across every category Microsoft builds or buys, from server racks to office buildings. Microsoft does not publish how much of the $88.2 billion went to AI, and it does not break out its capex by purpose in its filings.

What can be said is narrower and still significant. In the year Microsoft promised $80 billion for AI datacenters, its total capital spending passed that mark before the fourth quarter ended, and the CFO tied that spending, quarter after quarter, to cloud and AI demand.

The scale, against things that can be checked

$80 billion is more than the entire annual output of Vermont, Wyoming, Alaska, South Dakota or Montana, each of which produced less than that in 2024, according to the Bureau of Economic Analysis. It is roughly what North Dakota produces in a year ($80.1 billion).

It is also more than three years of NASA’s budget, which runs at about $25 billion a year.

In nuclear terms, the Barakah plant in the United Arab Emirates, four reactors built by Korea Electric Power Corporation, was financed at about $24.4 billion. At that cost, $80 billion would pay for more than 10 reactors of the same design. At the cost of the two most recent American reactors, Vogtle 3 and 4 in Georgia (about $35 billion for the pair), it would pay for four or five.

Microsoft was not the only one

Within weeks of the January post, Microsoft’s rivals published their own plans for calendar 2025. Alphabet said it expected to invest about $75 billion. Meta guided to between $60 billion and $65 billion. Amazon’s chief executive, Andy Jassy, said the company’s fourth quarter 2024 spending of $26.3 billion was a reasonable guide to its 2025 pace, which put Amazon above $100 billion for the year.

The four plans were not measured the same way. Microsoft’s figure was for a fiscal year that started in July, and the others were for calendar years. Each company also defines capital spending slightly differently. Even so, they point to the same thing: the largest technology companies committed, within a few weeks of each other, to spending at a pace none of them had reached before.

What came next

Fiscal 2025 turned out to be a starting point. Microsoft’s capital spending kept growing in fiscal 2026, and by mid 2026 the company was guiding to about $175 billion for calendar 2026, more than double the plan Brad Smith announced. We compare that figure with Alphabet’s in Microsoft vs Alphabet: the capex war. Where that money lands physically is a separate story, told county by county in places like West Virginia.

What we could not confirm

We could not find a Microsoft figure for how much of the $88.2 billion went to AI specifically, as opposed to other cloud capacity or offices. Microsoft has said only that the mix of spending was weighted toward cloud and AI. We also could not confirm how much of the fiscal 2025 total was cash paid in the year, as opposed to finance leases recognized at their start. Microsoft gives the cash figure each quarter, but we did not find it consolidated for the full year in the remarks we reviewed.

What to watch

The next useful document is Microsoft’s annual report on Form 10-K, which consolidates the cash paid for property and equipment for the full year. After that, the quarterly split between short-lived assets (servers and chips that wear out in a few years) and long-lived assets (buildings and land) will show how much of the spending has to be repeated as the hardware ages.

Frequently asked questions

How much did Microsoft say it would spend on AI in fiscal 2025?

About $80 billion on AI-enabled datacenters, according to a January 3, 2025 post by Microsoft president Brad Smith. More than half was to be spent in the United States.

How much did Microsoft actually spend in fiscal 2025?

$88.2 billion in capital expenditures including finance leases, adding up the four quarterly figures the CFO reported. That total covers all categories, not only AI datacenters.

Did Microsoft spend more than it promised?

Not in a way the documents can prove. The $80 billion was for AI datacenters; the $88.2 billion is total capex. Microsoft does not publish how much of the total went to AI.

What is Microsoft's fiscal year?

July to June. Fiscal 2025 ran from July 1, 2024 to June 30, 2025.

How does it compare with Alphabet, Meta and Amazon?

For calendar 2025, Alphabet guided to about $75 billion, Meta to between $60 billion and $65 billion, and Amazon to a pace above $100 billion. The figures use different periods and definitions, so they are close but not directly comparable.

Notes. All figures are in US dollars as reported. Capital expenditures including finance leases are as stated by Microsoft’s CFO on each quarterly earnings call; the annual totals are our sum of the four quarters. State GDP figures are 2024 current dollars from the Bureau of Economic Analysis.

Sources